This page list notable events in the SPEAR project in reverse chronological order. We hope to add pictures of the construction as they become available.
| October 2008 | SPEAR campaign, the final campaign in which Leicester will be involved, to be carried out jointly by Leicester, UNIS and EISCAT. This, at least in part, is a familiarisation/training activity which will transfer skills to UNIS personnel. |
| May 2008 | UNIS to take over SPEAR. Funding for SPEAR, along with all ground based STP facilities, was axed by PPARC/STFC at least partly in response to the £80m shortfall in funds due to the reorganisation of science support in the UK. Leicester has been seeking an organisation to take over the future operation of SPEAR in order to fully exploit the facility. We are pleased to announce that the Unviersity of Norway in Svalbard (UNIS) has agreed to take over ownership of SPEAR and we look forward to future scientific collaborations. Discussions as to how operations will be tansferred are ongoing. |
| October 2007 | Final UK SPEAR campaign carried out 10/10/07 - 21/10/07 |
| Aug/Sep 2007 | SPEAR campaign from 10/8/2007 and 7/9/2007 |
| Mar/Apr 2007 | New robidium frequency standard installed. Campaign carrried out 21/22007 - 13/3/2007 |
| Nov/Dec 2006 | SPEAR campaign 27/11/2006 - 15/12/2006 |
| October 2006 | First radar measurements made by SPEAR |
| July 2006 | SPEAR campaign 8/7/2006 - 24/7/2006 |
| Jan/Feb 2006 | SPEAR campaign 21/1/2006 - 4/2/2006 |
| Nov/Dec 2005 | SPEAR campaign 28/11/2005 - 9/12/2005 |
| Nov 2005 | Testing in conjuction with ESR/Power Station/Mine 7 between 1/11/2005 and 5/11/2005 to determine level of mains interference between the facilities. SPEAR gets clear bill of health. |
| June/July 2005 | Receiver calibrations and campaign 29/6/2005 - 19/7/2005 |
| April 2005 | SPEAR campaign 17/4/2005 - 28/4/2005 |
| December 2004 | SPEAR campaign 5/10/2004 - 16/12/2004 |
| October 2004 | First artificial irregularities generated by SPEAR observed with CUTLASS radars. Ionosonde installed at SPEAR site. |
| September 2004 | First operation of complete SPEAR system with all 48 transmitters working |
| August 2004 | Antenna array completed and final container unpacked and chimneys installed |
| May 2004 | Some construction pictures added (at last!) |
|
May 2004
|
Final transmitter container moved into position (pictures)
|
|
April 2004
|
Svbalbard ionosonde installed at the SPEAR site
|
|
April 2004
|
Experimental campaign carried out 7th April to 6th May. Artificial plasma lines generated by SPEAR observed with the ESR for the first time.
|
|
March 2004
|
SPEAR/EISCAT scheduling software in test phase
|
|
November 2003
|
SPEAR operates for the first time!
|
|
September 2003
|
Replacement transformer for substation arrives at the SPEAR site
|
|
Summer 2003
|
SPEAR antennas erected (pictures of the work in progress)
|
|
May 2002
|
Drilling completed and poles installed fot antenna foundations (above)
|
|
April 2002
|
SPEAR Workshop help at Leicester on 8th April - Report available here
|
|
March 2002
|
Testing of complete transmitter container confirms design and operation
|
|
January 2002
|
Announcement of SPEAR Workshop at Leicester on 8th April 2002
|
|
October 2001
|
Site survey completed. First picture of the site
|
|
September 2001
|
ESR interference tests look good!
|
|
March 2001
|
Funds released to enable bulk purchasing of components
|
|
February 2001
|
Transmitting licence issued by Post-og Teletilsynet
|
|
January 2001
|
Planning permission approved by the Govenor of Svalbard
|
|
January 2001
|
Submitted visualisation of SPEAR to suplement planning application
|
|
December 2000
|
Testing and approval of transmitter container cooling system
|
|
November 2000
|
Meeting with Post-og Teletilsynet to discuss details of transmitting licence application
|
|
October 2000
|
Successful test of Engineering Model operating at full power
|
|
August 2000
|
Identified possible site for SPEAR near to Mine 7 and the ESR
|
|
July 2000
|
8 4 kW Txs operated into model arrayat Bruntingthorpe field site
|
|
May 2000
|
Model antenna completed and tested at Bruntingthorpe field site
|
|
April 2000
|
Funding became available from PPARC for build phase
|
|
March 2000
|
Laboratory testing of 4 kW Tx and Tx/Rx switch
|
|
February 2000
|
Application for transmitting licence submitted to Post-og Teletilsynet
|
|
January 2000
|
Laboratory tests of high power Tx/Rx switch verify design and operation
|
|
January 1999
|
Laboratory testing of prototype new 1 kW PA module and Power Supply
|
|
January 1999
|
Successful testing of individual model antenna at Bruntingthorpe field site
|

These pages are administered by: WebMaster
Document last updated